The J mart Wirye BranchOpened in 2017
16.1 billion won
Total investment cost7.6 billion won
Land sale price6.0 billion won
Construction cost2.5 billion won
Interior, equipmentBuilding area2500평
Store area600평
Annual sales22 billion won
Parking available130 cars
The J market Dongtan Opened in 2021
33.2 billion won
Total investment cost12.4 billion won
Land sale price17.3 billion won
Construction cost3.5 billion won
Interior, equipmentBuilding area5600평
Store area860평
Annual sales30 billion won
Parking available200 cars
The J market Geomdan Scheduled to open in 2025
47.5 billion won
Total investment cost28.5 billion won
Land sale price15 billion won
Construction cost4 billion won
Interior, equipmentAnnual salesUndetermined
The J market Songdo Scheduled to open in 2026
30 billion won
Total investment costUndetermined
Land sale priceUndetermined
Construction costUndetermined
Interior, equipmentAnnual salesUndetermined